United States β€Ί Grid β€Ί Interconnection queues β€Ί New Mexico

SOLAR Β· WEST

Solar project Q181, San Juan County

Solar project Q181, San Juan County is a 50.0 MW solar request withdrawn in the West interconnection queue, in San Juan County, New Mexico, connecting to Arizona Public Service.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2011 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
Q181
Grid region
West (non-ISO utilities)
Utility / transmission owner
Arizona Public Service
Connection point (POI)
Four Corners 230kV substation
Location
San Juan County, New Mexico
Technology
Solar: 50.0 MW
Total requested
50.0 MW
Service type
NRIS and ERIS
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
12 January 2011
Proposed online date
June 2013

Location

Marker shows the centre of San Juan County; the queue data does not give exact sites.

Power plants in New Mexico Β· Transmission lines in New Mexico

Other requests in San Juan County