Onshore wind project J1194, Midland County

Onshore wind project J1194, Midland County is a 225 MW onshore wind request built and operating in the MISO interconnection queue, in Midland County, Michigan, connecting to METC.

Queue statusOperating
  1. PlanningQueued Apr 2019 (completed)
  2. ConsentedSep 2020 (completed)
  3. Construction (completed)
  4. OperatingNov 2021 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
J1194
Grid region
MISO (Midcontinent)
Utility / transmission owner
METC
Connection point (POI)
Murphy 138 kV Substation
Location
Midland County, Michigan
Technology
Wind: 225 MW
Total requested
225 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA Complete; Post GIA Status: In Service (with Provisional GIA)
Queue status
Operational
Entered queue
24 April 2019
Agreement signed
30 September 2020
Proposed online date
November 2021
Came online
November 2021

Location

Marker shows the centre of Midland County; the queue data does not give exact sites.

Power plants in Michigan · Transmission lines in Michigan

Other requests in Midland County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem