Solar project AG2-235, Delaware County

Solar project AG2-235, Delaware County is a 73.0 MW solar request withdrawn in the PJM interconnection queue, in Delaware County, Ohio, connecting to AEP.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2021 (completed)
  2. Withdrawn / abandonedDec 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AG2-235
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Lincoln-Berrywood 69 kV
Location
Delaware County, Ohio
Technology
Solar: 73.0 MW
Total requested
73.0 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
15 March 2021
Proposed online date
December 2024
Withdrawn
December 2024

Location

Marker shows the centre of Delaware County; the queue data does not give exact sites.

Power plants in Ohio Β· Transmission lines in Ohio

Other requests in Delaware County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem