πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί New York

GAS Β· NYISO

Brookhaven Energy

Brookhaven Energy is a 580 MW gas request withdrawn in the NYISO interconnection queue, in Suffolk County, New York, connecting to LIPA.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 1999 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
32
Grid region
NYISO (New York)
Utility / transmission owner
LIPA
Developer
American National Power
Connection point (POI)
Holbrook-Brookhaven 138kV
Location
Suffolk County, New York
Technology
Gas: 580 MW
Total requested
580 MW
Queue status
Withdrawn
Entered queue
22 November 1999

Location

Marker shows the centre of Suffolk County; the queue data does not give exact sites.

Power plants in New York Β· Transmission lines in New York

Other requests in Suffolk County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem