🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › California

ONSHORE WIND · CAISO

Daggett Wind Project II

Daggett Wind Project II is a 201 MW onshore wind request withdrawn in the CAISO interconnection queue, in San Bernardino County, California, connecting to SCE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2006 (completed)
  2. Withdrawn / abandonedMar 2012 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
156
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Lugo-Pisgah 230kV line
Location
San Bernardino County, California
Technology
Wind: 201 MW
Total requested
201 MW
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
5 December 2006
Proposed online date
March 2012
Withdrawn
March 2012

Location

Marker shows the centre of San Bernardino County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in San Bernardino County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem