🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

GAS · ERCOT

Brotman Power Station

Brotman Power Station is a 199 MW gas request built and operating in the ERCOT interconnection queue, in Brazoria County, Texas.

Queue statusOperating
  1. PlanningQueued Oct 2020 (completed)
  2. ConsentedOct 2021 (completed)
  3. Construction (completed)
  4. OperatingJun 2023 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
23INR0095
Grid region
ERCOT (Texas)
Developer
Brotman Generating, LLC
Connection point (POI)
tap 138kV Rosharon 44600 – 44440 Manvel. CNP station -138kV Archer Station
Location
Brazoria County, Texas
Technology
Gas: 199 MW
Total requested
199 MW
Study phase
IA
Queue status
Operational
Entered queue
22 October 2020
Agreement signed
1 October 2021
Proposed online date
June 2023
Came online
June 2023

Location

Marker shows the centre of Brazoria County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Brazoria County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem