United States βΊ Grid βΊ Interconnection queues βΊ New York
OTHER Β· NYISOModern Innovative Plant
Modern Innovative Plant is a 6.4 MW other request withdrawn in the NYISO interconnection queue, in Niagara County, New York, connecting to NM-NG.
Queue statusWithdrawn / abandoned
- PlanningQueued Jan 2007 (completed)
- Withdrawn / abandonedApr 2013 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 0239A
- Grid region
- NYISO (New York)
- Utility / transmission owner
- NM-NG
- Developer
- Innovative Energy System, Inc.
- Connection point (POI)
- Youngstown βΓͺ Sanborn 34.5kV
- Location
- Niagara County, New York
- Technology
- Other: 6.4 MW
- Total requested
- 6.4 MW
- Queue status
- Withdrawn
- Entered queue
- 31 January 2007
- Withdrawn
- April 2013
Location
Marker shows the centre of Niagara County; the queue data does not give exact sites.
Other requests in Niagara County
- Erie Canal BESSBattery storage Β· 230 MW Β· in study
- Lockport StorageBattery storage Β· 180 MW Β· in study
- Somerset SolarSolar Β· 125 MW Β· in study
- Buffalo Road Energy StorageBattery storage Β· 100 MW Β· in study
- Bear Ridge SolarSolar Β· 100 MW Β· in study
- Riverbank Power ABattery storage Β· 1,000 MW Β· withdrawn
- HuntleyGas Β· 752 MW Β· withdrawn
- SomersetCoal Β· 706 MW Β· withdrawn
- Ridge View Solar Energy CenterSolar Β· 350 MW Β· withdrawn
- Erie Canal BESSBattery storage Β· 230 MW Β· withdrawn
- Erie Canal BESSBattery storage Β· 230 MW Β· withdrawn
- Lighthouse WindOnshore wind Β· 201 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem