SOLAR · CAISO

Mojave Solar (Fka Harper Lake Solar)

Mojave Solar (Fka Harper Lake Solar) is a 250 MW solar request built and operating in the CAISO interconnection queue, in San Bernardino County, California, connecting to SCE.

Queue statusOperating
  1. PlanningQueued Aug 2006 (completed)
  2. ConsentedNov 2010 (completed)
  3. Construction (completed)
  4. OperatingDec 2014 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
125
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Coolwater-Kramer 230kv line
Location
San Bernardino County, California
Technology
Solar: 250 MW
Total requested
250 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Operational
Entered queue
22 August 2006
Agreement signed
18 November 2010
Proposed online date
August 2010
Came online
December 2014

Location

Marker shows the centre of San Bernardino County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in San Bernardino County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem