Battery storage project C2-93, Emery County

Battery storage project C2-93, Emery County is a 200 MW battery storage request withdrawn in the West interconnection queue, in Emery County, Utah, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2022 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
C2-93
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Developer
PacifiCorp
Connection point (POI)
Emery substation
Location
Emery County, Utah
Technology
Battery: 200 MW
Total requested
200 MW
Service type
NRIS and ERIS
Queue status
Withdrawn
Entered queue
13 May 2022
Proposed online date
May 2026

Location

Marker shows the centre of Emery County; the queue data does not give exact sites.

Power plants in Utah Β· Transmission lines in Utah

Other requests in Emery County