Birch Street - Combined Cycle

Birch Street - Combined Cycle is a 378 MW gas request withdrawn in the CAISO interconnection queue, in Orange County, California, connecting to SCE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2014 (completed)
  2. Withdrawn / abandonedJun 2014 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1079
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Ellis-Santiago line 220kV
Location
Orange County, California
Technology
Gas: 378 MW
Total requested
378 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
30 April 2014
Proposed online date
July 2018
Withdrawn
June 2014

Location

Marker shows the centre of Orange County; the queue data does not give exact sites.