GAS Β· NYISO

Faxton/ St. Luke

Faxton/ St. Luke is a 2.2 MW gas request withdrawn in the NYISO interconnection queue, in Herkimer County, New York, connecting to NM-NG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2006 (completed)
  2. Withdrawn / abandonedJul 2008 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
0225B
Grid region
NYISO (New York)
Utility / transmission owner
NM-NG
Developer
Burrstone Energy
Connection point (POI)
TBD
Location
Herkimer County, New York
Technology
Gas: 2.2 MW
Total requested
2.2 MW
Queue status
Withdrawn
Entered queue
15 September 2006
Withdrawn
July 2008

Location

Marker shows the centre of Herkimer County; the queue data does not give exact sites.

Power plants in New York Β· Transmission lines in New York

Other requests in Herkimer County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem