United States βΊ Grid βΊ Interconnection queues βΊ Indiana
SOLAR Β· PJMSolar project AF2-212, Jay County
Solar project AF2-212, Jay County is a 150 MW solar request withdrawn in the PJM interconnection queue, in Jay County, Indiana, connecting to Dayton.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2020 (completed)
- Withdrawn / abandonedApr 2021 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AF2-212
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- Dayton
- Connection point (POI)
- Shelby 138 kV
- Location
- Jay County, Indiana
- Technology
- Solar: 150 MW
- Total requested
- 150 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study
- Queue status
- Withdrawn
- Entered queue
- 25 March 2020
- Proposed online date
- December 2023
- Withdrawn
- April 2021
Location
Marker shows the centre of Jay County; the queue data does not give exact sites.
Other requests in Jay County
- Skycrest Solar Energy CenterSolar Β· 155 MW Β· agreement signed
- Blackford Solar Energy ProjectSolar Β· 150 MW Β· agreement signed
- Sun Chief Solar FarmSolar Β· 100 MW Β· agreement signed
- New Jay PV & BESSSolar + storage Β· 39.0 MW Β· agreement signed
- Bitter Ridge Wind FarmOnshore wind Β· 12.6 MW Β· agreement signed
- Solar + storage project AI1-081, Jay CountySolar + storage Β· 100 MW Β· in study
- Battery storage project AH2-227, Jay CountyBattery storage Β· 75.0 MW Β· in study
- Solar project AH2-223, Jay CountySolar Β· 50.0 MW Β· in study
- Battery storage project AH2-371, Jay CountyBattery storage Β· 50.0 MW Β· in study
- Solar project AI2-422, Jay CountySolar Β· 12.0 MW Β· in study
- Solar project AI2-423, Jay CountySolar Β· 12.0 MW Β· in study
- Bitter Ridge Wind FarmOnshore wind Β· 130 MW Β· built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem