Battery storage project SRP-Q46

Battery storage project SRP-Q46 is a 25.0 MW battery storage request built and operating in the West interconnection queue, connecting to Salt River Project.

Queue statusOperating
  1. PlanningQueued Aug 2018 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingTarget May 2021 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
SRP-Q46
Grid region
West (non-ISO utilities)
Utility / transmission owner
Salt River Project
Connection point (POI)
Agua Fria-Barcelona 69 kV Line
Technology
Battery: 25.0 MW
Total requested
25.0 MW
Study phase
IA Executed
Queue status
Operational
Entered queue
17 August 2018
Proposed online date
May 2021

Location

Marker shows the centre of County; the queue data does not give exact sites.