United States › Grid › Interconnection queues › California

SOLAR · CAISO

Ivanpah Segs 3

Ivanpah Segs 3 is a 132 MW solar request built and operating in the CAISO interconnection queue, in San Bernardino County, California, connecting to SCE.

Queue statusOperating
  1. PlanningQueued Jun 2007 (completed)
  2. ConsentedJul 2010 (completed)
  3. Construction (completed)
  4. OperatingDec 2013 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
233
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Ivanpah Substation 115kV
Location
San Bernardino County, California
Technology
Solar: 132 MW
Total requested
132 MW
Study phase
Executed
Queue status
Operational
Entered queue
27 June 2007
Agreement signed
30 July 2010
Proposed online date
June 2013
Came online
December 2013

Location

Marker shows the centre of San Bernardino County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in San Bernardino County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem