United States › Grid › Interconnection queues › New York

SOLAR + STORAGE · NYISO

Pivot Burnell

Pivot Burnell is a 20.0 MW solar + storage request withdrawn in the NYISO interconnection queue, in Clinton County, New York, connecting to NYSEG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2022 (completed)
  2. Withdrawn / abandonedApr 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1422
Grid region
NYISO (New York)
Utility / transmission owner
NYSEG
Developer
Pivot Energy Development LLC
Connection point (POI)
Lyon Mountain - Saranac 115 kV
Location
Clinton County, New York
Technology
Solar: 20.0 MW · Battery
Total requested
20.0 MW
Queue status
Withdrawn
Entered queue
31 August 2022
Withdrawn
April 2023

Location

Marker shows the centre of Clinton County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Clinton County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem