United States › Grid › Interconnection queues › Texas
SOLAR + STORAGE · ERCOTAggie Solar Project SLF
Aggie Solar Project SLF is a 104 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Reeves County, Texas.
Queue statusIn planning
- PlanningQueued Feb 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jun 2027 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 26INR0388
- Grid region
- ERCOT (Texas)
- Developer
- reNRG TX 8 LLC
- Connection point (POI)
- POI: COYOTE SPRINGS SUBSTATION - 138KV BUS NUMBER : 38113 COUNTY : REEVES POI LOCATION: 31.396675, -103.6252777
- Location
- Reeves County, Texas
- Technology
- Solar: 104 MW · Battery
- Total requested
- 104 MW
- Study phase
- SS Completed, FIS Completed, No IA
- Queue status
- Active
- Entered queue
- 2 February 2024
- Proposed online date
- June 2027
Location
Marker shows the centre of Reeves County; the queue data does not give exact sites.
Other requests in Reeves County
- Cantaloupe SolarSolar · 307 MW · agreement signed
- August Draw SolarSolar · 250 MW · agreement signed
- Bracero Pecan StorageBattery storage · 238 MW · agreement signed
- Tolivar Power Plant (TEF- Due Diligence)Gas · 225 MW · agreement signed
- Elm Street BESS2Battery storage · 10.0 MW · agreement signed
- Saddleback AGR1Other · 10.0 MW · agreement signed
- Coyote Springs AGR1Other · 10.0 MW · agreement signed
- County Road BESSBattery storage · 9.9 MW · agreement signed
- Elm Street BESSBattery storage · 9.9 MW · agreement signed
- Wolf Bone North Energy CenterGas · 1,204 MW · in study
- Kilby1 Part 4 Large Block Simple CycleGas · 950 MW · in study
- Exergy Energy West Texas Natural Gas Reciprocating Power IGas · 400 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem