Onshore wind project R57, Carroll County

Onshore wind project R57, Carroll County is a 100 MW onshore wind request withdrawn in the MISO interconnection queue, in Carroll County, Iowa.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2009 (completed)
  2. Withdrawn / abandonedJan 2014 (project stopped here)
  3. ConsentedJan 2014 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
R57
Grid region
MISO (Midcontinent)
Connection point (POI)
Victory 161 kV Substation
Location
Carroll County, Iowa
Technology
Wind: 100 MW
Total requested
100 MW
Study phase
SPA - SIS
Queue status
Withdrawn
Entered queue
30 March 2009
Agreement signed
6 January 2014
Proposed online date
January 2010
Withdrawn
January 2014

Location

Marker shows the centre of Carroll County; the queue data does not give exact sites.

Power plants in Iowa Β· Transmission lines in Iowa

Other requests in Carroll County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem