United States β€Ί Grid β€Ί Interconnection queues β€Ί Pennsylvania

SOLAR Β· PJM

Solar project AH1-284, Adams County

Solar project AH1-284, Adams County is a 2.0 MW solar request withdrawn in the PJM interconnection queue, in Adams County, Pennsylvania, connecting to PPL.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2021 (completed)
  2. Withdrawn / abandonedDec 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AH1-284
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PPL
Connection point (POI)
West Willow 12 kV
Location
Adams County, Pennsylvania
Technology
Solar: 2.0 MW
Total requested
2.0 MW
Service type
Energy only (ERIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
10 September 2021
Proposed online date
December 2023
Withdrawn
December 2024

Location

Marker shows the centre of Adams County; the queue data does not give exact sites.

Power plants in Pennsylvania Β· Transmission lines in Pennsylvania

Other requests in Adams County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem