United States β€Ί Grid β€Ί Interconnection queues β€Ί Alabama

GAS Β· SOUTHEAST

Gas project IC-092, Autauga County

Gas project IC-092, Autauga County is a 630 MW gas request withdrawn in the Southeast interconnection queue, in Autauga County, Alabama, connecting to Southern Company.

Queue statusWithdrawn / abandoned
  1. Planning (completed)
  2. Withdrawn / abandonedJun 2003 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IC-092
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Snowdoun - S. Bessemer 500 kV line
Location
Autauga County, Alabama
Technology
Gas: 630 MW
Total requested
630 MW
Service type
Energy only (ERIS)
Study phase
Withdrawn
Queue status
Withdrawn
Withdrawn
June 2003

Location

Marker shows the centre of Autauga County; the queue data does not give exact sites.

Power plants in Alabama Β· Transmission lines in Alabama

Other requests in Autauga County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem