Hydro project 363, Madison County

Hydro project 363, Madison County is a 3.8 MW hydro request built and operating in the West interconnection queue, in Madison County, Montana, connecting to NorthWestern Energy.

Queue statusOperating
  1. PlanningQueued May 2019 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingMar 2021 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
363
Grid region
West (non-ISO utilities)
Utility / transmission owner
NorthWestern Energy
Connection point (POI)
Existing Madison Substation
Location
Madison County, Montana
Technology
Hydro: 3.8 MW
Total requested
3.8 MW
Service type
Network resource (NRIS)
Study phase
IA Executed
Queue status
Operational
Entered queue
10 May 2019
Proposed online date
March 2021
Came online
March 2021

Location

Marker shows the centre of Madison County; the queue data does not give exact sites.

Power plants in Montana · Transmission lines in Montana

Other requests in Madison County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem