Paragon II Wind Generation

Paragon II Wind Generation is a 150 MW onshore wind request withdrawn in the NYISO interconnection queue, in Steuben County, New York, connecting to NYSEG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2005 (completed)
  2. Withdrawn / abandonedAug 2008 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
204
Grid region
NYISO (New York)
Utility / transmission owner
NYSEG
Developer
Clipper Windpower Dev. Co. Inc.
Connection point (POI)
Avoca - Hillside 230kV
Location
Steuben County, New York
Technology
Wind: 150 MW
Total requested
150 MW
Queue status
Withdrawn
Entered queue
27 October 2005
Withdrawn
August 2008

Location

Marker shows the centre of Steuben County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Steuben County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem