United States βΊ Grid βΊ Interconnection queues βΊ Texas
SOLAR Β· ERCOTAmelia Dairy Solar
Amelia Dairy Solar is a 94.1 MW solar request withdrawn in the ERCOT interconnection queue, in Wood County, Texas.
Queue statusWithdrawn / abandoned
- Planning (completed)
- Withdrawn / abandonedMar 2023 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 25INR0163
- Grid region
- ERCOT (Texas)
- Developer
- Amelia Dairy Solar LLC
- Connection point (POI)
- 48566 Winnsboro 138 kV
- Location
- Wood County, Texas
- Technology
- Solar: 94.1 MW
- Total requested
- 94.1 MW
- Study phase
- FIS & SS Incomplete
- Queue status
- Withdrawn
- Proposed online date
- November 2025
- Withdrawn
- March 2023
Location
Marker shows the centre of Wood County; the queue data does not give exact sites.
Other requests in Wood County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem