SOLAR Β· ERCOT

Amelia Dairy Solar

Amelia Dairy Solar is a 94.1 MW solar request withdrawn in the ERCOT interconnection queue, in Wood County, Texas.

Queue statusWithdrawn / abandoned
  1. Planning (completed)
  2. Withdrawn / abandonedMar 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
25INR0163
Grid region
ERCOT (Texas)
Developer
Amelia Dairy Solar LLC
Connection point (POI)
48566 Winnsboro 138 kV
Location
Wood County, Texas
Technology
Solar: 94.1 MW
Total requested
94.1 MW
Study phase
FIS & SS Incomplete
Queue status
Withdrawn
Proposed online date
November 2025
Withdrawn
March 2023

Location

Marker shows the centre of Wood County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Wood County