United States › Grid › Interconnection queues › New Mexico
SOLAR · WESTSolar project SGI-PNM-2010-13, Luna County
Solar project SGI-PNM-2010-13, Luna County is a 9.0 MW solar request built and operating in the West interconnection queue, in Luna County, New Mexico, connecting to Public Service Company of New Mexico.
Request details
- Queue ID
- SGI-PNM-2010-13
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Public Service Company of New Mexico
- Connection point (POI)
- PNM-RGD Hondale Feeder 12
- Location
- Luna County, New Mexico
- Technology
- Solar: 9.0 MW
- Total requested
- 9.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- First Revised SGIA executed 2/4/2013
- Queue status
- Operational
- Entered queue
- 7 July 2010
- Agreement signed
- 4 February 2013
Location
Marker shows the centre of Luna County; the queue data does not give exact sites.
Power plants in New Mexico · Transmission lines in New Mexico
Other requests in Luna County
- AN100SSolar · 100 MW · agreement signed
- AN50BBattery storage · 50.0 MW · agreement signed
- Solar project SGI-PNM-2017-08, Luna CountySolar · 11.0 MW · agreement signed
- Solar project SGI-PNM-2017-09, Luna CountySolar · 8.3 MW · agreement signed
- LD200SBSolar + storage · 200 MW · in study
- Me199SBSolar + storage · 199 MW · in study
- Me195SBSolar + storage · 195 MW · in study
- LA130S ProjectSolar + storage · 130 MW · in study
- LA300WOnshore wind · 300 MW · suspended
- Macho Springs Solar PVSolar · 50.0 MW · built
- Solar project TI-15-0227, Luna CountySolar · 25.0 MW · built
- LA450SSolar · 450 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem