United States › Grid › Interconnection queues › Texas
BATTERY STORAGE · ERCOTAtticus Energy Storage
Atticus Energy Storage is a 103 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Sutton County, Texas.
Queue statusIn planning
- PlanningQueued Mar 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Mar 2027 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 27INR0236
- Grid region
- ERCOT (Texas)
- Developer
- Atticus Energy Storage
- Connection point (POI)
- Tap 69 KV 6570 Bond Road - 6513 Sonora
- Location
- Sutton County, Texas
- Technology
- Battery: 103 MW
- Total requested
- 103 MW
- Study phase
- SS Completed, FIS Started, No IA
- Queue status
- Active
- Entered queue
- 29 March 2024
- Proposed online date
- March 2027
Location
Marker shows the centre of Sutton County; the queue data does not give exact sites.
Other requests in Sutton County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem