Forward WF

Forward WF is a 29.4 MW onshore wind request built and operating in the PJM interconnection queue, in Somerset County, Pennsylvania, connecting to PENELEC.

Queue statusOperating
  1. PlanningQueued Jul 2002 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingMar 2008 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
I13
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PENELEC
Connection point (POI)
Hooversville 115kV
Location
Somerset County, Pennsylvania
Technology
Wind: 29.4 MW
Total requested
29.4 MW
Service type
Energy only (ERIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Operational
Entered queue
30 July 2002
Proposed online date
March 2008
Came online
March 2008

Location

Marker shows the centre of Somerset County; the queue data does not give exact sites.