SOLAR + STORAGE · ERCOT

Zunkerville Solar

Zunkerville Solar is a 201 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Karnes County, Texas.

Queue statusIn planning
  1. PlanningQueued Dec 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
28INR0443
Grid region
ERCOT (Texas)
Developer
Zunkerville Energy, LLC
Connection point (POI)
#5725 PAWNEE SWITCHING STATION 345kV
Location
Karnes County, Texas
Technology
Solar: 201 MW · Battery
Total requested
201 MW
Study phase
SS Started, FIS Started, No IA
Queue status
Active
Entered queue
2 December 2025
Proposed online date
June 2028

Location

Marker shows the centre of Karnes County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Karnes County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem