United States › Grid › Interconnection queues › New York
SOLAR + STORAGE · NYISONorth Norwich Solar
North Norwich Solar is a 120 MW solar + storage request withdrawn in the NYISO interconnection queue, in Chenango County, New York, connecting to NYSEG.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2022 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 1437
- Grid region
- NYISO (New York)
- Utility / transmission owner
- NYSEG
- Developer
- Northland Power U.S. Projects
- Connection point (POI)
- County Line-East Norwich Tap 115 kV NYSEG
- Location
- Chenango County, New York
- Technology
- Solar: 120 MW · Battery
- Total requested
- 120 MW
- Queue status
- Withdrawn
- Entered queue
- 14 September 2022
Location
Marker shows the centre of Chenango County; the queue data does not give exact sites.
Other requests in Chenango County
- High Bridge WindOnshore wind · 101 MW · in study
- Sherburne StorageBattery storage · 40.0 MW · in study
- Puckett SolarSolar · 20.0 MW · built
- Puckett SolarSolar · 20.0 MW · built
- JennisonCoal · 650 MW · withdrawn
- JennisonCoal · 536 MW · withdrawn
- Solar Generation Jennison Revitalization FacilitySolar · 118 MW · withdrawn
- Brookfield Wind EnergyOnshore wind · 100 MW · withdrawn
- Regan SolarSolar · 20.0 MW · withdrawn
- Puckett SolarSolar · 20.0 MW · withdrawn
- High Bridge BatteryBattery storage · 5.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem