United States › Grid › Interconnection queues › New York

SOLAR + STORAGE · NYISO

North Norwich Solar

North Norwich Solar is a 120 MW solar + storage request withdrawn in the NYISO interconnection queue, in Chenango County, New York, connecting to NYSEG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2022 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1437
Grid region
NYISO (New York)
Utility / transmission owner
NYSEG
Developer
Northland Power U.S. Projects
Connection point (POI)
County Line-East Norwich Tap 115 kV NYSEG
Location
Chenango County, New York
Technology
Solar: 120 MW · Battery
Total requested
120 MW
Queue status
Withdrawn
Entered queue
14 September 2022

Location

Marker shows the centre of Chenango County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Chenango County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem