United States › Grid › Interconnection queues › Utah

COAL · WEST

Coal project 270-A, Emery County

Coal project 270-A, Emery County is a 16.2 MW coal request built and operating in the West interconnection queue, in Emery County, Utah, connecting to PacifiCorp.

Queue statusOperating
  1. PlanningQueued Apr 2009 (completed)
  2. ConsentedMay 2010 (completed)
  3. Construction (completed)
  4. OperatingTarget Jan 2012 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
270-A
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Developer
PacifiCorp Energy
Connection point (POI)
Huntington Power Plant, Huntington, Utah
Location
Emery County, Utah
Technology
Coal: 16.2 MW
Total requested
16.2 MW
Service type
Energy only (ERIS)
Study phase
IA signed May 19, 2010
Queue status
Operational
Entered queue
30 April 2009
Agreement signed
19 May 2010
Proposed online date
January 2012

Location

Marker shows the centre of Emery County; the queue data does not give exact sites.

Power plants in Utah · Transmission lines in Utah

Other requests in Emery County