Solar project AC2-058, Tuscarawas County

Solar project AC2-058, Tuscarawas County is a 16.4 MW solar request withdrawn in the PJM interconnection queue, in Tuscarawas County, Ohio, connecting to AEP.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2017 (completed)
  2. Withdrawn / abandonedJul 2017 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AC2-058
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Newcomerstown-N. Philly 69kV
Location
Tuscarawas County, Ohio
Technology
Solar: 16.4 MW
Total requested
16.4 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
16 February 2017
Proposed online date
December 2018
Withdrawn
July 2017

Location

Marker shows the centre of Tuscarawas County; the queue data does not give exact sites.