United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Hydro interconnection queue in the USA (2017 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown6722 MW
Active in queue722 MW6 requests
Agreement signed76.4 MW5 requests
Withdrawn7131 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

6 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Hydro project G0566, Lincoln County
Hydro
646 MWIn study Lincoln, MTWest Jun 2017target 2022
Hydro project 323, Marion County
Hydro
27.0 MWAgreement signed Marion, TNSoutheast Aug 2017target 2022
Hydro project 322, Marion County
Hydro
27.0 MWAgreement signed Marion, TNSoutheast Aug 2017target 2021
Hydro project 320, Marion County
Hydro
11.0 MWAgreement signed Marion, TNSoutheast Aug 2017target 2019
Hydro project 321, Marion County
Hydro
11.0 MWAgreement signed Marion, TNSoutheast Aug 2017target 2021
Hydro project 973, Franklin County
Hydro Β· City of Preston
0.4 MWAgreement signed Franklin, IDWest Nov 2017target 2018

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)