United States β€Ί Grid β€Ί Interconnection queues β€Ί Wyoming

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in Wyoming (2015 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown81,700 MW
Active in queue400 MW2 requests
Agreement signed120 MW1 requests
Withdrawn1125 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

8 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project 712, Converse County
Onshore wind Β· Cedar Springs Transmission LLC
520 MWOperating Converse, WYWest Oct 2015target 2020
Onshore wind project 713, Converse County
Onshore wind Β· Cedar Springs Transmission LLC
350 MWOperating Converse, WYWest Oct 2015target 2025
Onshore wind project 706, Carbon County
Onshore wind Β· PacifiCorp
250 MWOperating Carbon, WYWest Sep 2015target 2020
Onshore wind project 707, Carbon County
Onshore wind Β· PacifiCorp
250 MWOperating Carbon, WYWest Sep 2015target 2020
Onshore wind project 708, Carbon County
Onshore wind Β· PacifiCorp
250 MWOperating Carbon, WYWest Sep 2015target 2020
Solar project 720, Sweetwater County
Solar Β· Sweetwater Solar, LLC
80.0 MWOperating Sweetwater, WYWest Nov 2015target 2018
Hydro project 677, Johnson County
Hydro Β· City of Buffalo
0.2 MWOperating Johnson, WYWest Jun 2015target 2016
Gas project 646, Fremont County
Gas Β· American Industrial Laundry
0.0 MWOperating Fremont, WYWest Mar 2015target 2016

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)