OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Washington (2012 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown81,300 MW
Active in queue375 MW1 requests
Agreement signed0.0 MW0 requests
Withdrawn81,300 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

8 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project G0471, Klickitat County
Gas
590 MWWithdrawn / abandoned Klickitat, WAWest Apr 2012target 2016
Gas project 419, Cowlitz County
Gas
375 MWWithdrawn / abandoned Cowlitz, WAWest Mar 2012target 2015
Gas project 35, Whitman County
Gas
200 MWWithdrawn / abandoned Whitman, WAWest Mar 2012target 2014
Onshore wind project 36, Whitman County
Onshore wind
105 MWWithdrawn / abandoned Whitman, WAWest Sep 2012target 2016
Other project 408, Yakima County
Other Β· WKN Chopin, LLC
20.0 MWWithdrawn / abandoned Yakima, WAWest Jan 2012target 2013
Solar project 422, Yakima County
Solar
5.0 MWWithdrawn / abandoned Yakima, WAWest Mar 2012target 2015
Solar project 421, Yakima County
Solar
5.0 MWWithdrawn / abandoned Yakima, WAWest Mar 2012target 2015
Hydro project 37, Adams County
Hydro
0.4 MWWithdrawn / abandoned Adams, WAWest Oct 2012target 2013

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)