United States β€Ί Grid β€Ί Interconnection queues β€Ί Virginia

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in Virginia (2020 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown6147 MW
Active in queue1,676 MW29 requests
Agreement signed1,100 MW18 requests
Withdrawn18912.4 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

6 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Bartonsville Energy Facility
Solar
50.0 MWOperating Frederick, VAPJM Feb 20202024
Norge Solar
Solar
20.0 MWOperating James City, VAPJM Sep 20202023
Dry Bridge Energy Center
Battery storage
20.0 MWOperating Chesterfield, VAPJM Feb 20202023
Winterberry Solar
Solar
20.0 MWOperating Gloucester, VAPJM Feb 20202024
Camellia Solar
Solar
19.9 MWOperating Gloucester, VAPJM Jan 20202025
Scott 1 BESS
Solar + storage
17.0 MWOperating Powhatan, VAPJM Mar 20202023

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)