Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown61,765 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn2796 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

6 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Greensville Generating Facility
Gas
1,681 MWOperating Greensville, VAPJM Oct 20132018
Clinch River Power Plant
Gas
20.0 MWOperating Russell, VAPJM Feb 20132016
Clinch River Power Plant
Gas
20.0 MWOperating Russell, VAPJM Feb 20132016
Hecate Energy Cherrydale
Solar
20.0 MWOperating Northampton, VAPJM Dec 20132017
HP Hood Generation Facility
Gas
12.0 MWOperating Rockingham, VAPJM Oct 20132015
Offshore wind project Z1-068, City Of Virginia Beach County
Offshore wind
12.0 MWOperating City Of Virginia Beach, VAPJM Oct 20132020

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)