United States βΊ Grid βΊ Interconnection queues βΊ Utah
OCTARY USA Β· INTERCONNECTION QUEUESInterconnection queue in Utah (2021 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Solar + storage project Q85, Juab County Solar + storage Β· Intermountain Power Agency |
550 MW | In study |
| Solar + storage project C1-11, Emery County Solar + storage Β· Drunkards Wash Energy, LLC |
450 MW | Agreement signed |
| Solar + storage project C1-50, Utah County Solar + storage Β· Mosida Solar, LLC |
400 MW | Paused / redesign |
| Solar + storage project C1-51, Juab County Solar + storage Β· Thirsty Valley Solar Energy LLC |
300 MW | Paused / redesign |
| Onshore wind project Q86, Millard County Onshore wind Β· Intermountain Power Agency |
300 MW | In study |
| Solar + storage project C1-39, Washington County Solar + storage Β· REBU BN, LLC |
300 MW | Agreement signed |
| Battery storage project Q83, Millard County Battery storage Β· Intermountain Power Agency |
220 MW | In study |
| Solar + storage project C1-34, Utah County Solar + storage Β· Quicksilver Solar, LLC |
200 MW | Agreement signed |
| Solar + storage project C1-16, Millard County Solar + storage Β· Neptune Solar Energy Park LLC |
199 MW | Paused / redesign |
| Solar + storage project C1-54, Utah County Solar + storage Β· Pinyon Creek Solar LLC |
199 MW | Paused / redesign |
| Solar + storage project C1-14, Emery County Solar + storage Β· Muddy Creek Energy, LLC |
120 MW | Paused / redesign |
| Solar + storage project C1-10, Emery County Solar + storage Β· Emery Bull Creek Energy, LLC |
45.0 MW | Paused / redesign |
| Wind + storage project C1-04, Salt Lake County Wind + storage |
6.0 MW | In study |
| Onshore wind project C1-58, Salt Lake County Onshore wind |
2.0 MW | In study |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)