Completed queue projects in Utah (2012 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown570.7 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn13926 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 450, Millard County
Solar Β· Pavant Solar, LLC
50.0 MWOperating Millard, UTWest Dec 2012target 2015
Geothermal project 415, Beaver County
Geothermal Β· Thermo No. 1 BE-01, LLC
11.0 MWOperating Beaver, UTWest Mar 2012target 2013
Other project 432, Salt Lake County
Other Β· eBay, Inc.
6.3 MWOperating Salt Lake, UTWest Aug 2012target 2013
Solar project 438, Tooele County
Solar Β· Tooele Army Depot
1.8 MWOperating Tooele, UTWest Aug 2012target 2016
Onshore wind project 439, Tooele County
Onshore wind Β· Tooele Army Depot
1.6 MWOperating Tooele, UTWest Aug 2012target 2016

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)