United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Texas (2016 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown122,229 MW
Active in queue2,229 MW12 requests
Agreement signed1,297 MW8 requests
Withdrawn356,196 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

12 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Vaquero 1 Wind
Onshore wind Β· Enerverse
400 MWIn study Zapata, TXERCOT Apr 2016target 2027
Canyon Wind
Onshore wind Β· Canyon Wind Energy, LLC
309 MWAgreement signed Scurry, TXERCOT May 2016target 2025
Armstrong Wind
Onshore wind Β· Big Sky Energy
253 MWPaused / redesign Armstrong, TXERCOT May 2016target 2020
Tri-X Solar 1 SLF
Solar + storage Β· Crane I Solar Electric, LLC
202 MWAgreement signed Crane, TXERCOT Nov 2016target 2027
Monte Alto 2 Wind
Onshore wind Β· Terra-Gen
200 MWAgreement signed Willacy, TXERCOT Nov 2016target 2027
Maryneal Wind
Onshore wind Β· Maryneal Windpower, LLC
182 MWAgreement signed Nolan, TXERCOT May 20162021
Tri-County Solar
Solar
178 MWPaused / redesign Crane, TXERCOT Oct 2016
Grandfalls Solar
Solar + storage Β· Nextera
176 MWAgreement signed Upton, TXERCOT May 2016target 2027
Monte Alto I
Onshore wind Β· Terra-Gen
142 MWAgreement signed Willacy, TXERCOT Nov 2016target 2028
Holstein 2 Solar
Solar + storage Β· 229HD 8me LLC
101 MWIn study Nolan, TXERCOT Dec 2016target 2028
Horse13 CallD repower
Onshore wind Β· Nextera
44.0 MWAgreement signed Taylor, TXERCOT Oct 2016target 2026
HHGT repower Horse13+CallD
Onshore wind Β· Nextera
44.0 MWAgreement signed Taylor, TXERCOT Oct 2016target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)