United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in Texas (2014 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5804 MW
Active in queue1,797 MW5 requests
Agreement signed405 MW2 requests
Withdrawn285,821 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GEN-2014-040, Castro County
Onshore wind
320 MWOperating Castro, TXSPP Sep 20142016
RE Maplewood 2a Solar
Solar Β· Recurrent Energy
222 MWOperating Pecos, TXERCOT Oct 20142021
Lockett Wind
Onshore wind Β· Lincoln Clean
184 MWOperating Wilbarger, TXERCOT Sep 20142019
Lamesa Solar B (Phase II) IVORY
Solar Β· OCI Solar
50.0 MWOperating Dawson, TXERCOT Jun 20142018
RE Maplewood 2b Solar
Solar Β· Recurrent Energy
28.0 MWOperating Pecos, TXERCOT Oct 20142021

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)