United States β€Ί Grid β€Ί Interconnection queues β€Ί Tennessee

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Tennessee (2021 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown53,530 MW
Active in queue3,530 MW5 requests
Agreement signed241 MW3 requests
Withdrawn121,269 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project 489, Roane County
Gas
1,689 MWIn study Roane, TNSoutheast Dec 2021target 2026
Gas project 483, Stewart County
Gas
1,600 MWIn study Stewart, TNSoutheast Oct 2021target 2025
Solar + storage project 469, Henderson County
Solar + storage
125 MWAgreement signed Henderson, TNSoutheast Mar 2021target 2028
Solar project 482, Cumberland County
Solar
110 MWAgreement signed Cumberland, TNSoutheast Oct 2021target 2027
Nuclear project 471, Hamilton County
Nuclear
6.0 MWAgreement signed Hamilton, TNSoutheast Mar 2021target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)