United States β€Ί Grid β€Ί Interconnection queues β€Ί Tennessee

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Tennessee (2017 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown6173 MW
Active in queue173 MW6 requests
Agreement signed173 MW6 requests
Withdrawn5749 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

6 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project 333, Shelby County
Solar + storage
74.0 MWAgreement signed Shelby, TNSoutheast Oct 2017target 2024
Hydro project 323, Marion County
Hydro
27.0 MWAgreement signed Marion, TNSoutheast Aug 2017target 2022
Hydro project 322, Marion County
Hydro
27.0 MWAgreement signed Marion, TNSoutheast Aug 2017target 2021
Gas project 332, Shelby County
Gas
23.0 MWAgreement signed Shelby, TNSoutheast Oct 2017target 2018
Hydro project 320, Marion County
Hydro
11.0 MWAgreement signed Marion, TNSoutheast Aug 2017target 2019
Hydro project 321, Marion County
Hydro
11.0 MWAgreement signed Marion, TNSoutheast Aug 2017target 2021

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)