United States β€Ί Grid β€Ί Interconnection queues β€Ί Tennessee

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Tennessee (2022 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown91,021 MW
Active in queue357 MW3 requests
Agreement signed357 MW3 requests
Withdrawn91,021 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

9 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project 524, Jefferson County
Battery storage
250 MWWithdrawn / abandoned Jefferson, TNSoutheast Oct 2022
Solar project 507, Grundy County
Solar
160 MWWithdrawn / abandoned Grundy, TNSoutheast Jul 2022
Solar + storage project 505, Franklin County
Solar + storage
146 MWWithdrawn / abandoned Franklin, TNSoutheast Jun 2022
Battery storage project 513, Maury County
Battery storage
145 MWWithdrawn / abandoned Maury, TNSoutheast Aug 2022target 2027
Solar project 503, Gibson County
Solar
70.0 MWWithdrawn / abandoned Gibson, TNSoutheast Jun 2022target 2024
Solar project 496, Haywood County
Solar
70.0 MWWithdrawn / abandoned Haywood, TNSoutheast Mar 2022target 2024
Solar project 495, Fayette County
Solar
70.0 MWWithdrawn / abandoned Fayette, TNSoutheast Mar 2022target 2024
Solar project 511, Crockett County
Solar
55.0 MWWithdrawn / abandoned Crockett, TNSoutheast Aug 2022target 2025
Solar project 518, Madison County
Solar
55.0 MWWithdrawn / abandoned Madison, TNSoutheast Sep 2022target 2025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)