United States βΊ Grid βΊ Interconnection queues βΊ South Carolina
OCTARY USA Β· INTERCONNECTION QUEUESWithdrawn queue requests in South Carolina (2019 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Solar project 131, Laurens County Solar |
160 MW | Withdrawn / abandoned |
| Solar project 122, Aiken County Solar |
103 MW | Withdrawn / abandoned |
| Solar project 126, Berkeley County Solar |
100 MW | Withdrawn / abandoned |
| Solar project 125, Berkeley County Solar |
100 MW | Withdrawn / abandoned |
| Solar project 123, Aiken County Solar |
81.6 MW | Withdrawn / abandoned |
| Solar project 133, Dorchester County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project 136, Georgetown County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project 127, Clarendon County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project 134, Orangeburg County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project 128, Sumter County Solar |
74.9 MW | Withdrawn / abandoned |
| Solar project 129, Aiken County Solar |
60.0 MW | Withdrawn / abandoned |
| Solar project 62472, Greenwood County Solar |
55.0 MW | Withdrawn / abandoned |
| Solar project 63666, Laurens County Solar |
55.0 MW | Withdrawn / abandoned |
| Solar project 121, Marlboro County Solar |
19.9 MW | Withdrawn / abandoned |
| Solar project 31552, Horry County Solar |
7.6 MW | Withdrawn / abandoned |
| Solar project 25592, Lee County Solar |
2.0 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)