United States βΊ Grid βΊ Interconnection queues βΊ Pennsylvania
OCTARY USA Β· INTERCONNECTION QUEUESWithdrawn queue requests in Pennsylvania (2024 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Black Cherry BESS Battery storage Β· Black Cherry Wind Power, LLC |
400 MW | Withdrawn / abandoned |
| PA-Hockenberry LLC Solar Β· PA-Hockenberry LLC |
400 MW | Withdrawn / abandoned |
| Black Cherry Wind 1 Onshore wind Β· Black Cherry Wind Power, LLC |
350 MW | Withdrawn / abandoned |
| PA-Fritz Kiln LLC Solar Β· PA-Fritz Kiln LLC |
300 MW | Withdrawn / abandoned |
| Black Cherry Wind 2 Onshore wind Β· Black Cherry Wind Power, LLC |
150 MW | Withdrawn / abandoned |
| Winner Solar Solar Β· Winner Solar, LLC |
120 MW | Withdrawn / abandoned |
| Winterberry Wind Onshore wind Β· Winterberry Wind LLC |
100 MW | Withdrawn / abandoned |
| Winterberry Wind Onshore wind Β· Winterberry Wind LLC |
50.0 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)