United States βΊ Grid βΊ Interconnection queues βΊ Pennsylvania
OCTARY USA Β· INTERCONNECTION QUEUESWithdrawn queue requests in Pennsylvania (2016 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Renaissance Energy Center Gas |
1,140 MW | Withdrawn / abandoned |
| Nuclear project J649, Dauphin County Nuclear |
829 MW | Withdrawn / abandoned |
| Gas project AC1-081, Luzerne County Gas |
180 MW | Withdrawn / abandoned |
| Onshore wind project AC1-186, Somerset County Onshore wind |
138 MW | Withdrawn / abandoned |
| Onshore wind project AC1-187, Potter County Onshore wind |
117 MW | Withdrawn / abandoned |
| Gas project AB2-074, Snyder County Gas |
113 MW | Withdrawn / abandoned |
| Solar project AB2-071, Adams County Solar |
100 MW | Withdrawn / abandoned |
| Solar project AC1-211, Fulton County Solar |
70.0 MW | Withdrawn / abandoned |
| Waymart Wind II Onshore wind |
67.3 MW | Withdrawn / abandoned |
| Solar project AC1-217, Franklin County Solar |
55.0 MW | Withdrawn / abandoned |
| Onshore wind project AC2-004, Somerset County Onshore wind |
50.8 MW | Withdrawn / abandoned |
| Brookview Solar I Solar |
35.0 MW | Withdrawn / abandoned |
| Gas project AC1-184, Delaware County Gas |
35.0 MW | Withdrawn / abandoned |
| Solar project AC1-151, Luzerne County Solar |
20.0 MW | Withdrawn / abandoned |
| Mason Dixon Wind Farm Onshore wind |
19.4 MW | Withdrawn / abandoned |
| Pine Grove Solar Solar |
18.0 MW | Withdrawn / abandoned |
| Gas project AC1-011, Clarion County Gas |
18.0 MW | Withdrawn / abandoned |
| Gas project AC1-183, Berks County Gas |
12.0 MW | Withdrawn / abandoned |
| Gas project AB2-046, Washington County Gas |
0.5 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)