Completed queue projects in Pennsylvania (2010 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown9106 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn691,635 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

9 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Beacon Power Flywheel Station
Battery storage
20.0 MWOperating Luzerne, PAPJM Apr 20102014
Conemaugh Generating Station
Coal
20.0 MWOperating Indiana, PAPJM May 20102012
Conemaugh Generating Station
Coal
20.0 MWOperating Indiana, PAPJM May 20102012
Roxbury Solar Project
Solar
13.5 MWOperating Franklin, PAPJM Mar 20102019
Grays Ferry Cogeneration Partnership
Gas
13.0 MWOperating Philadelphia, PAPJM Apr 20102013
Dart Container
Other
11.4 MWOperating Lancaster, PAPJM Mar 20102012
Cumberland County Landfill
Other
4.8 MWOperating Cumberland, PAPJM May 20102012
Other project W2-014, Philadelphia County
Other
2.0 MWOperating Philadelphia, PAPJM May 20102014
Tolna Unit 2
Other
0.9 MWOperating York, PAPJM Jul 20102011

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)