United States βΊ Grid βΊ Interconnection queues βΊ Oregon
OCTARY USA Β· INTERCONNECTION QUEUESInterconnection queue in Oregon (2011 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Gas project 11-046, Multnomah County Gas |
518 MW | Paused / redesign |
| Onshore wind project 11-043, Umatilla County Onshore wind |
400 MW | Paused / redesign |
| Gas project 11-045, Multnomah County Gas |
213 MW | Paused / redesign |
| Onshore wind project 11-040, Gilliam County Onshore wind |
200 MW | Paused / redesign |
| Onshore wind project 11-039, Gilliam County Onshore wind |
200 MW | Paused / redesign |
| Other project 11-042, Jefferson County Other |
37.0 MW | Paused / redesign |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)