United States βΊ Grid βΊ Interconnection queues βΊ Oregon
OCTARY USA Β· INTERCONNECTION QUEUESWithdrawn queue requests in Oregon (2021 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Solar + storage project G0697, Crook County Solar + storage |
3,600 MW | Withdrawn / abandoned |
| Solar + storage project G0696, Crook County Solar + storage |
2,600 MW | Withdrawn / abandoned |
| Solar + storage project G0698, Crook County Solar + storage |
1,800 MW | Withdrawn / abandoned |
| Solar + storage project G0700, Crook County Solar + storage |
1,200 MW | Withdrawn / abandoned |
| Solar + storage project G0701, Crook County Solar + storage |
1,200 MW | Withdrawn / abandoned |
| Other project 21-095, Deschutes County Other |
1,000 MW | Withdrawn / abandoned |
| Battery storage project 21-105, Washington County Battery storage |
800 MW | Withdrawn / abandoned |
| Solar project G0674, Crook County Solar |
600 MW | Withdrawn / abandoned |
| Solar + storage project 21-096, Lake County Solar + storage |
400 MW | Withdrawn / abandoned |
| Solar + storage project G0677, Gilliam County Solar + storage |
400 MW | Withdrawn / abandoned |
| Solar + storage project C1-24, Klamath County Solar + storage |
400 MW | Withdrawn / abandoned |
| Solar + storage project C1-23, Klamath County Solar + storage Β· Sugar Pine Solar Project LLC |
300 MW | Withdrawn / abandoned |
| Solar + storage project 21-097, Morrow County Solar + storage |
200 MW | Withdrawn / abandoned |
| Solar + storage project C1-19, Marion County Solar + storage |
199 MW | Withdrawn / abandoned |
| Solar + storage project C1-45, Morrow County Solar + storage |
100 MW | Withdrawn / abandoned |
| Solar project G0719, Sherman County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project 595, Union County Solar |
50.0 MW | Withdrawn / abandoned |
| Solar + storage project C1-31, Klamath County Solar + storage |
35.0 MW | Withdrawn / abandoned |
| Solar project G0690, Jefferson County Solar |
20.0 MW | Withdrawn / abandoned |
| Other project G0666, Morrow County Other |
4.0 MW | Withdrawn / abandoned |
| Other project 1234, Jackson County Other |
0.8 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)