United States β€Ί Grid β€Ί Interconnection queues β€Ί Oregon

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Oregon (2021 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2115.0 GW
Active in queue19.1 GW32 requests
Agreement signed2,037 MW8 requests
Withdrawn2115.0 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

21 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project G0697, Crook County
Solar + storage
3,600 MWWithdrawn / abandoned Crook, ORWest Sep 2021target 2032
Solar + storage project G0696, Crook County
Solar + storage
2,600 MWWithdrawn / abandoned Crook, ORWest Sep 2021target 2030
Solar + storage project G0698, Crook County
Solar + storage
1,800 MWWithdrawn / abandoned Crook, ORWest Sep 2021target 2025
Solar + storage project G0700, Crook County
Solar + storage
1,200 MWWithdrawn / abandoned Crook, ORWest Sep 2021target 2025
Solar + storage project G0701, Crook County
Solar + storage
1,200 MWWithdrawn / abandoned Crook, ORWest Sep 2021target 2025
Other project 21-095, Deschutes County
Other
1,000 MWWithdrawn / abandoned Deschutes, ORWest Mar 2021target 2025
Battery storage project 21-105, Washington County
Battery storage
800 MWWithdrawn / abandoned Washington, ORWest Aug 2021target 2023
Solar project G0674, Crook County
Solar
600 MWWithdrawn / abandoned Crook, ORWest Mar 2021target 2030
Solar + storage project 21-096, Lake County
Solar + storage
400 MWWithdrawn / abandoned Lake, ORWest Mar 2021target 2025
Solar + storage project G0677, Gilliam County
Solar + storage
400 MWWithdrawn / abandoned Gilliam, ORWest Apr 2021target 2023
Solar + storage project C1-24, Klamath County
Solar + storage
400 MWWithdrawn / abandoned Klamath, ORWest May 2021target 2025
Solar + storage project C1-23, Klamath County
Solar + storage Β· Sugar Pine Solar Project LLC
300 MWWithdrawn / abandoned Klamath, ORWest May 2021target 2030
Solar + storage project 21-097, Morrow County
Solar + storage
200 MWWithdrawn / abandoned Morrow, ORWest Apr 2021target 2023
Solar + storage project C1-19, Marion County
Solar + storage
199 MWWithdrawn / abandoned Marion, ORWest May 2021target 2025
Solar + storage project C1-45, Morrow County
Solar + storage
100 MWWithdrawn / abandoned Morrow, ORWest May 2021target 2024
Solar project G0719, Sherman County
Solar
80.0 MWWithdrawn / abandoned Sherman, ORWest Dec 2021target 2025
Solar project 595, Union County
Solar
50.0 MWWithdrawn / abandoned Union, ORWest Jan 2021
Solar + storage project C1-31, Klamath County
Solar + storage
35.0 MWWithdrawn / abandoned Klamath, ORWest May 2021target 2025
Solar project G0690, Jefferson County
Solar
20.0 MWWithdrawn / abandoned Jefferson, ORWest Sep 2021target 2022
Other project G0666, Morrow County
Other
4.0 MWWithdrawn / abandoned Morrow, ORWest Jan 2021target 2021
Other project 1234, Jackson County
Other
0.8 MWWithdrawn / abandoned Jackson, ORWest Aug 2021

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)