United States β€Ί Grid β€Ί Interconnection queues β€Ί Oregon

OCTARY USA Β· INTERCONNECTION QUEUES

Projects with signed interconnection agreements in Oregon (2016 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown3757 MW
Active in queue1,232 MW10 requests
Agreement signed757 MW3 requests
Withdrawn734,870 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

3 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project G0539, Deschutes County
Solar
600 MWAgreement signed Deschutes, ORWest May 2016target 2022
Solar project 734, Crook County
Solar Β· Aurora Solar, LLC
102 MWAgreement signed Crook, ORWest Mar 2016target 2025
Solar + storage project 731, Crook County
Solar + storage Β· Prineville Solar Energy LLC
55.0 MWAgreement signed Crook, ORWest Mar 2016target 2025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)