United States βΊ Grid βΊ Interconnection queues βΊ Oklahoma
OCTARY USA Β· INTERCONNECTION QUEUESInterconnection queue in Oklahoma (2022 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Gas project GI-104, Payne County Gas |
460 MW | Agreement signed |
| Gas project GI-103, Creek County Gas |
460 MW | Agreement signed |
| Solar project GEN-2022-016, Woodward County Solar |
288 MW | In study |
| Solar project GEN-2022-055, Grady County Solar |
200 MW | In study |
| Solar project GEN-2022-098, Johnston County Solar |
200 MW | In study |
| Battery storage project GEN-2022-017, Woodward County Battery storage |
150 MW | In study |
| Battery storage project GEN-2022-012, Woodward County Battery storage |
100 MW | In study |
| Solar project GEN-2022-071, Pittsburg County Solar |
90.8 MW | In study |
| Battery storage project GEN-2023-SR5, Dewey County Battery storage |
85.0 MW | Agreement signed |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)