United States β€Ί Grid β€Ί Interconnection queues β€Ί Oklahoma

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Oklahoma (2019 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown4457 MW
Active in queue457 MW4 requests
Agreement signed457 MW4 requests
Withdrawn10836 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

4 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project GEN-2019-012, Woodward County
Battery storage
200 MWAgreement signed Woodward, OKSPP May 2019target 2027
Solar project GEN-2019-045, Woods County
Solar
155 MWAgreement signed Woods, OKSPP May 2019target 2028
Gas project GI-78, Mayes County
Gas
52.0 MWAgreement signed Mayes, OKSoutheast Jan 2019target 2020
Gas project GI-77, Mayes County
Gas
50.0 MWAgreement signed Mayes, OKSoutheast Jan 2019target 2019

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)